1. TRANSIT TYPE ACCOMODATION
AT TARAPUR
B.A.R.C B.A.R.C DEPARTMENT GUPTA & CO COMPLETE W.PROFING 500.00SQ.MTR MAY 1983
2. TARDEO TOWERS AT TARDEO TARDEO TOWERS JOGLEKAR JOGLEKAR & NOOR COMPLETE W.PROOFING 2000.00SQ.MTR JAN 1984
3. JUMBO DARSHAN
CO-OP HSG SOC AT ANDHERI.
JUMBO DARSHAN SOCIETY ---------------- SELF COMPLETE CIVIL REPARING 6000.00SQ.MTR MAR 1985
4. RESIDENTIAL COMPLEX AT PANVEL O.N.G.C FEROZ KUDIANWALA VATAN SINGH & CO COMPLETE W.PROOFING 9000.00SQ.MT DEC 1986
5. GHATKOPAR HIGH LEVEL RESERVIOR B.M.C B.M.C DEPARTMENT UNION CONST COMPLETE W.PROOFING 7100.00SQ.MTR MAY 1987
6. MARTIME TRAINING INSTITUTE AT POWAI S.C.I DEPARTMENT DALAL CONSULTANTS &ENGINEERS P.LTD COMPLETE W.PROOFING 9000.00SQ.MTR MAY 1988
7. G.W.N.D STAFF QUARTERS AT WADALA & SEWREE AREA. B.P.T ---------------- TENDER NO.E-72/88 COMPLETE CIVIL & REPARING 20000.00SQ.MTR MAR 1989
8. PROPOSED FRUIT & VEGETABLE MARKET AT VASHI A.P.M.C SHASHI PRABHU & ASSOCIATES UNITY CONST CO & AJANTA BUILDERS BASEMENT BOX- TYPE 2500.00SQ.MTR & COMPLETE W.PROOFING 50000.00SQ.MTR DEC 1990
9. MASTER BALANCING RESERVOIR AT BHIWANDI. B.M.C B.M.C DEPARTMENT GOLANI & CO COMPLETE W.PROOFING 45000.00SQ.MTR DEC 1991
10. MASS HOUSING COMPLEX FOR MAHADA AT MAJASWADI. M.A.H.A.D.A MASTER ASSOCIATES UNITY CONST CO. COMPLETE W.PROOFING 35000.00 SQ.MTR DEC 1992
11. ANTOP HILL WAREHOUSING PROJECT AT WADALA. ANTOP HILL WAREHOUSING GHERJI EASTERN DALAL CONSULTANT & ENGINEERS LTD BASEMENT BOX METHOD 15000.00SQ.MTR & COMPLETE W.PROOFING OCT 1993
12. MASS HOUSING COMPLEX AT KOPARKHAIRNE C.I.D.C.O FEROZ KUDIANWALA N.B.C.C COMPLETE W.PROOFING 30000.00SQ.MTR APR 1994
13. TRADE CENTRE BUILDING FOR M.I.D.C AT WAGALE ESTATE, THANE. M.I.D.C M.I.D.C DEPARTMENT K.J.CONST CO BASEMENT BOX METHOD 3500.00SQ.MTR & COMPLETE W.PROOFING DEC 1995
14. PROVISION OF SERVICE BLOCK & A/C PLANT ROOM/TECHNICAL ACCOMODATION/ RESIDENTIAL TRANSIST ACCOMODATION/ CENTRAL WORKSHOP & MI ROOM/ COMMUNITY HALL & SHOPPING COMPLEX/ ADMINISTRATIVE ACCOMODATION & ALLIED SERVICES FOR N.M.R.L AT AMBERNATH D.R.D.O D.R.D.O DEPARTMENT QUALITY CONST CO COMPLETE W.PROOFING 15000.00SQ.MTR DEC 1996
15. CONSTRUCTION OF COMMERCIAL PREMISES AT SEEPZ ANDHERI M.I.D.C M.I.D.C DEPARTMENT KULKARNI & CO.
& KLASSIC CONSTRUCTION
BASEMENT BOX METHOD 15000.00SQMTR& COMPLETE W.PROOFING MAR 1997
16. PROPOSED ELECTRONIC TELEPHONE EXCHANGE AT PEDDAR ROAD M.T.N.L FEROZ KUDIANWALA K.J.CONST CO BASAMENT BOX METHOD & COMPLETE W.PROOFING JUN 1998
17. PROVIDING CEMENT BASED WATERPROOFING AT F-SOUTH WARD FROM 01-10-1996 TO 30-09-1999 M.C.G.M ---------------- UNDER DY.CE (BC ) CITY W.O & DEAN K.E.M HOSPITAL COMPLETE W.PROOFING & REPARING WORK SEP 1999
18. MATOSHREE SPORTS COMPLEX AT JOGESHWARI VIKHROLI LINK ROAD MATOSHREE TRUST SHASHI PRABHU & ASSOCIATES DEEPAK SAMANT CONST COMPLETE W.PROOFING SEP 2000
19. CONSTRUCTION OF INFOTECH PARK AT SEEPZ ANDHERI M.I.D.C M.I.D.C DEPARTMENT GOLANI BROTHERS BASEMENT BOX METHOD 10000.00SQMTR & COMPLETE W.PROOFING JUNE 2001
20. .CONSTRUCTION OF NATIONAL GAMES STADIUM AT GACHBOLI, HYDERABAD GOVT OF ANDHRA PRADESH SHASHI PRABHU & ASSOCIATES NAGARJUNA CONST CO. COMPLETE W.PROOFING JUNE 2001
21. CONSTRUCION OF M.I.D.C BUILDING AT MAHAPE NAVI MUMBAI M.I.D.C MASTER ASSOCIATES UNITY CONST CO. BASEMENT BOX METHOD & COMPLETE W.PROOFING 16000.00SQ.MTR JAN 2002
22. CONSTRUCTION OF 3 RESIDENTIAL TOWER COMPLEX AT NEELKANTH VALLEY GHATKOPAR KALANDI, NILGIRI, HIMGIRI NEELKANTH GROUP   DIRECT WORK COMPLETE W.PROOFING 9000 SQMTR JUN 2003
23. CONSTRUCTION OF S.R.D TENEMENTS FOR M.U.T.P AT MAHUL VILLAGE CHEMBUR GR+5 FLOORS 24 BUILDINGS. M.M.R.D.A STUP CONSULTANT ADVANCE CONST CO. PVT LTD COMPLETE W.PROOFING DEC 2004
24. CONSTRUCTION OF D.D.A HOUSING PROJECT GR+5 FLOORS 100 BUILDINGS AT NARELA, DELHI D.D.A D.D.A DEPARTMENT UNITY INFRA PROJECTS LTD. COMPLETE W.PROOFING JAN 2005
25. CONSTRUCTION OF RABALE RAILWAY STATION AT RABALE, NAVI MUMBAI KOKAN RAILWAY RATAN.J. BATLIBOI UNITY INFRA PROJECTS LTD COMPLETE W.PROOFING DEC 2005
26. CONSTRUCTION OF SHOPPING MALL AT HADAPSAR PUNE RUNWAL GROUP SANJAY PURI UNITY INFRA PROJECT LTD DOUBLE BASEMENT BOX METHOD 7000 SQ. MTR APR 2006
27. CONSTRUCTION OF HI-LIFE SHOPPING MALL AT SANTACRUZ NEELKANTH GROUP DESPANDE PARANCHPAE ASSOCIATES DIRECT WORK DOUBLE BASEMENT BOX METHOD & COMPLETE W.PROOFING SEP 2006
28. CONSTRUCTION OF NATIONAL CENTRE FOR PRIMATE BREEDING & RESEARCH AT MAJLIPADA VASAI NCPBR RATAN BATLIBOI SAAG RR BASEMENT BOX-METHOD SEP 2006
29. CONSTRUCTION OF SHOPPING MALL & COMMERCIAL CENTRE AT KANDIVALI GROWEL 101 GROUP NITIN PARULKAR LAXMANBHAI CONSTRUCTION AND T.K.CONSTRUCTION BASEMENT BOX-METHOD AND COMPLETE W.PROOFING OCT 2006
30. CONSTRUCTION OF COMMERCIAL PREMISES "INDIA BULLS" AT JUPITER MILL COMPOUND PAREL INDIA BULLS GROUP HAFEEZ CONTRACTOR UNITY INFRA PROJECT LTD & AHLUWALIA CONTRACTS(I) LTD DOUBLE BASEMENT BOX TYPE W. PROOFING 35000.00 SQ. MTR DEC 2006
31. CONSTRUCTION OF RESIDENTIAL COMPLEX AT NEELKANTH GREENS NEELKANTH GROUP D.S.ASSOCIATES DIRECT WORK COMPLETE W.PROOFING FEB 2007
32. CONSTRUCTION OF RESIDENTIAL TOWER OF GR+16 FLOORS RELIANCE HAFEEZ CONTRACTOR G.M.BIJLANI COMPLETE W.PROOFING OF 2 TOWERS FEB 2007
33. CONSTRUCTION OF RESIDENTIAL BUILDINGS FOR KOHINOOR CITY AT KURLA KOHINOOR DEVELOPERS D.S. ASSOCIATES QUALITY CONSTRUCTIONS COMPLETE W.PROOFING MAY 2007
34. CONSTRUCTION OF TWO RESIDENTIAL TOWERS (G+23) FOR MAHINDRA EMINENT AT GOREGOAN MAHINDRA LIFE SPACES HAFEEZ CONTRACTOR ADVANCE CONSTRUCTION PVT LTD. COMPETE W.PROOFING JUNE 2007
35. CONSTRUCTION OF M.A.P. RESIDENTIAL PROJECT FOR AIR FORCE OF INDIA 125 BUILDINGS G+3 STOREY AT JODHPUR AIR FORCE OF INDIA S.K. INTEGRAL CONSULTANT S.E.W. CONST LTD COMPLETE W.PROOFING AUG 2007
36. CONSTRUCTION OF COMMERCIAL MALL CUM RESIDENTIAL TOWERS OF 28 AND 32 STOREYS AT MUMBAI CENTRAL BALWAS GROUP QUTUB MANDIWAL UNITY INFRA PROJECT LTD COMPLETE W.PROOFING APR 2008
37. CONSTRUCTION OF RESIDENTIAL COMPLEX, NEELKANTH PALMS. NEELKANTH GROUP DESPANDE PARANCHPAE ASSOCIATES SELF COMPLETE W.PROOFING JULY 2007
38. CONSTRUCTION OF COMMERCIAL MALL CUM RESIDENTIAL TOWERS OF 28 AND 32 STOREYS AT MUMBAI CENTRAL BALWAS GROUP QUTUB MANDIWAL UNITY INFRA PROJECT LTD COMPLETE W.PROOFING APR 2008
39. PROPOSED CONSTRUCTION OF SPECIALITY HOSPITAL AT NIMS, HYDERABAD NIMS HOSPITAL N.A UNITY INFRAPROJECTS LTD BASEMENT BY BOX TYPE W. PROOFING 6500.00 SQ. MTR AND COMPLETE W.PROOFING APR 2008
40.
PROPOSED CONSTRUCTION OF BIG MALL AT THANE, MUMBAI G.CORP DESIGN PLUS JUNITY INFRA PROJECTSLTD COMPLETE W.PROOFING AUG 2008
41. PROPOSED CONSTRUCTION OF MALL AT HARI HAR MANDIR DHANAGANJ, NAGPUR N.A P.G.PHATKE & ASSOCIATES UNITY INFRAPROJECTS LTD TRIPLE BASEMENT BOX TYPE W. PROOFING 21100.00 SQ. MTR AND COMPLETE W.PROOFING MAR 2008
42. PROPOSED CONSTRUCTION OF MALL AT JARIPATKA, NAGPUR N.A N.A UNITY INFRAPROJECTS LTD BASEMENT BY BOX TYPE W. PROOFING 5500.00 SQ. MTR AND COMPLETE W.PROOFING JUNE 2008
43. PROPOSED CONSTRUCTION OF HIGH COURT BENCH AT GULBARGA N.A N.A UNITY INFRAPROJECTS LTD COMPLETE W.PROOFING JUNE 2008
44. WATERPROOFING WORK FOR SRA PROJECT AT MAHUL G+7 STOREY DYNAMIX REALTY SHAH & DOMASIA MAN INFRA CONSTRUCTION LTD COMPLETE W.PROOFING NOV 2008
45. CONSTRUCTION OF LIC BUILDING AT BANDRA KURLA COMPLEX LIC OF INDIA SHASHI PRABHU & ASSOCIATES UNITY INFRA PROJECT LTD COMPLETE W.PROOFING DEC 2008
46. CONSTRUCTION OF SPORTS COMPLEX AT WORLI (NSCI) NSCI SHASHI PRABHU & ASSOCIATES UNITY INFRA PROJECT BASEMENT BOX METHOD & COMPLETE W.PROOFING FEB 2009
47. CONSTRUCTION OF STAFF QUARTERS FOR DRDO AT OZHAR NASIK DRDO M.N. DASTUR QUICK BUILDER COMPLETE W. PROOFING FEB 2009
48. CONSTRUCTION OF SHOPPING MALL AT HADAPSAR PUNE RUNWAL GROUP SANJAY PURI UNITY INFRA PROJECT LTD DOUBLE BASEMENT BOX METHOD 7000 SQ. MTR MAR 2007
49. PROPOSED CONSTRUCTION OF MALL AT HARI HAR MANDIR DHANAGANJ, NAGPUR N.A P.G.PHATKE & ASSOCIATES UNITY INFRAPROJECTS LTD TRIPLE BASEMENT BOX TYPE W. PROOFING 21100.00 SQ. MTR AND COMPLETE W.PROOFING MAR 2008
50. CONSTRUCTION OF BUNGLOWS AT MULLA BAUG. GHODBUNDER ROAD, THANE RAVECHII & NEELKANTH GROUP HAFEEZ CONTRACTOR SELF COMPLETE W.PROOFING MAR 2008
51. PROPOSED CONSTRUCTION OF SPECIALITY HOSPITAL AT NIMS, HYDERABAD NIMS HOSPITAL N.A UNITY INFRAPROJECTS LTD BASEMENT BY BOX TYPE W. PROOFING 6500.00 SQ. MTR AND COMPLETE W.PROOFING APR 2008
52. PROPOSED CONSTRUCTION OF MALL AT JARIPATKA, NAGPUR N.A N.A UNITY INFRAPROJECTS LTD BASEMENT BY BOX TYPE W. PROOFING 5500.00 SQ. MTR AND COMPLETE W.PROOFING JUNE 2008
53. PROPOSED CONSTRUCTION OF HIGH COURT BENCH AT GULBARGA GOVT OF INDIA N.A UNITY INFRAPROJECTS LTD COMPLETE W.PROOFING JUNE 2008
54. BOX TYPE WATERPROOFING WORK AT GODREJ IT PARK (P2) AT VIKHROLI MUMBAI GODREJ D.V.JOSHI JMC PROJECTS (INDIA) LTD BASEMENT BY BOX TYPE W. PROOFING 10000.00SQ.MTR JUNE 2008
55. CONSTRUCTION OF COMMERCIAL PREMISES "INDIA BULLS" AT JUPITER MILL COMPOUND PAREL INDIA BULLS GROUP HAFEEZ CONTRACTOR UNITY INFRA PROJECT LTD & AHLUWALIA CONTRACTS(I) LTD DOUBLE BASEMENT BOX TYPE W. PROOFING 35000.00 SQ. MTR JUL 2008
56. CONSTRUCTION OF TWO RESIDENTIAL TOWERS (G+23) FOR MAHINDRA EMINENT AT GOREGOAN MAHINDRA LIFE SPACES HAFEEZ CONTRACTOR ADVANCE CONSTRUCTION PVT LTD. COMPETE W.PROOFING JUNE 2009
57. PROPOSED CONSTRUCTION OF BIG MALL AT THANE, MUMBAI G.CORP DESIGN PLUS UNITY INFRA PROJECTS LTD COMPETE W.PROOFING AUG 2008
58. WATERPROOFING WORK FOR SRA PROJECT AT MAHUL G+7 STOREY 11 NOS BLGD DYNAMIX REALTY SHAH & DOMASIA MAN INFRA CONSTRUCTION LTD COMPETE W.PROOFING NOV 2009
59. CONSTRUCTION OF SHOPPING MALL & COMMERCIAL CENTRE AT KANDIVALI GROWEL 101 GROUP NITIN PARULKAR LAXMANBHAI CONSTRUCTION AND T.K.CONSTRUCTION BASEMENT BOX-METHOD AND COMPLETE W.PROOFING FEB 2010
60. PROPOSED CONSTRUCTION OF AMANORA PARK, PUNE CITY CORPORATION LTD UNITY INFRAPROJECTS LTD COMPLETE W.PROOFING APR 2010
61. BASEMENT WATERPROOFING WORK USING ROUGH SHAHBAD LADI AT PROPOSED REDEVOPLEMENT OF R.N.COOPERHOSPITAL AT VILE PARLE (W) M.C.G.M G.D.SAMBHARE & CO UNITY INFRA PROJECT LTD BOX TYPE WATERPROOFING. AUG 2010
62. CONSTRUCTION AND BEAUTIFICATION OF DADAR SEWRAGE TREATMENT CENTRE M.C.G.M M.C.G.M GOLANI BROTHERS COMPETE W.PROOFING OCT 2010
63. CONSTRUCTION OF RESIDENTIAL TOWERS (G+28) AT MULLABAUG THANE PH I & II NEELKANTH INFRA LTD SAAKAR SELF COMPETE W.PROOFING OCT 2010
64. CONSTRUCTION OF NATIONAL CENTRE FOR PRIMATE BREEDING & RESEARCH AT MAJLIPADA VASAI NCPBR RATAN BATLIBOI SAAG RR BASEMENT BOX-METHOD OCT 2010
65. PROPOSED CONST OF ELITE HOTEL AT KOHINOOR CITY AT VIDYAVIHAR, KURLA (W) KOHINOOR GROUP QUALITY HEIGHTCON PVT LTD COMPLETE W.PROOFING DEC 2010
66. CONSTRUCTION OF SEA BIRD PROJECT AT KARWAR GOVT OF INDIA MECON UNITY INFRAPROJECTS LTD COMPLETE W.PROOFING JAN 2011
67. CONSTRUCTION OF RESEARCH & DEVELOPMENT BUILDING FOR CIPLA LTD AT VIKHROLI CILPA KAMAL MALLIK B.E.BILLIMORIA & CO LTD DOUBLE BASEMENT BY BOX TYPE W. PROOFING 16000.00SQ.MTR AND COMPLETE W.PROOFING JUNE 2011
68. CONSTRUCION OF HOSPITAL BLDG. FOR TATA CANCER AT PAREL TATA HOSP. PAREL HAFEEZ CONTRACTOR UNITY INFRA PROJECT LTD BASEMENT BY CRYSTALLIZATION AND COMPLETE W.PROOFING JULY 2011
69. CONSTRUCTION OF BIO SCHOOL & LECT HALL COMPLEX AT IIT POWAI I.I.T.B Satish M Madival GOLANI BROTHERS COMPLETE W.PROOFING NOV 2011
70. CONST OF MAHINDRA SPLENDOUR TOWERS A, B & C MLDL HAFEEZ CONTRACTOR B.E.BILLIMORIA & CO LTD COMPLETE W.PROOFING FEB 2012
71. CONSTRUCTION OF VEDANTA CANCER HOSPITAL & RESEARCH CENTER AT RAIPUR VEDANTA MRF LTD. KAMAL MALLIK B.E.BILLIMORIA & CO LTD BASEMENT & SUPERSTRUCTURE COMPLETE W.PROOFING (CHEMICAL & CEMENT BASED) APRIL 2012
72. PROPOSED CONST OF RESENDITALCOMPLEX SAMRUDDHI SUNSHINE AT BHANDUP. GROUP SUNSHINE PVT LTD QUALITY HEIGHTCON PVT LTD BOX TYPE W.PROOFING MAY 2012
73. WATERPROOFING WORK AT PROPOSED CONSTRUCTION OF HOUSES FOR THE TOWNSHIP OF RAIL COACH FACTORY AT RAE BARELI (U.P) GOVT OF INDIA (RAILWAYS) RAJNISH AGARWAL UNITY INFRA PROJECTS LTD TERRACE WATERPROOFING. MAY 2012
74. CONSTRUCTION OF TWO RESIDENTIAL TOWERS (G+18 & G+20), PODIUM, SWIMMING POOL & CLUB HOUSE AT THANE VRAJ GLOBAL ENTERPRISES ARCHETYPE CONSULRANTS PVT LTD SELF COMPLETE W.PROOFING JUNE 2012
75. WATERPROOFING WORK AT NALASOPORA VIRAR RLY YARD P I & P II M.R.V.C ERA INFRA ENGG LTD BOX TYPE WATERPROOFING. JULY 2012
76. CONSTRUCTION OF HOSTEL BUILDING, B-23AT IIT POWAI I.I.T.B HAFEEZ CONTRACTOR GOLANI BROTHERS COMPLETE W.PROOFING JULY 2012